|
Asking the Right Questions of the Team
In the last article, we saw how the analysis of project problems
mirrors quite well the situation a doctor is confronted with. We
took our cue from this and developed a diagnostic approach toward
project control. We saw that there were four broad types of problems,
each reflecting a commonly found situation. In order to determine
which of these types are responsible for the problems we might be
seeing, we need to formulate a precise set of questions.
The situation as a task begins is shown as follows. This assumes
that it has not been delayed by problems in predecessor tasks. The
dark bar shows the original forecast, now elevated to the status
of the 'Plan" or 'Baseline'. The upper bar continues to be
the current best forecast.

As this task continues we should be tracking its progress. Thus
the first question we ask our team at each update period is:
"How much progress has been achieved to date?"
Percent
Complete
This question is usually answered in the form of a percentage. Now
there are many interpretations of what a percentage can mean but
let us be quite clear about this: The only meaningful measure is
one that which provides a description of output as opposed to input
- to some degree of approximation. We do not want our team to tell
us they are 50% complete because half of the time (an input measure)
has elapsed. We do not need help with this quantity from anyone.
Similarly, we don't want to be told that 50% has been achieved because
half of the allotted hours of effort have been consumed.
We are interested in a measure of progress toward completion. Of
course this implies we know what completion is. This can only be
the case if we had a clear and shared understanding with the team
as to what the deliverable (which defines 100%) of this task is.
This is a vital part of the planning and one that cannot be ignored
if progress measures are to mean anything.
So, a percentage measures something physical. This is not always
easy. In work involving research, design, writing, software development
and similar activities, this is quite elusive. In work relating
more closely to the visible and physical world, measures are easier
to find.
In any event we should not claim too much precision in this. Percentages
expressed to the nearest decile are probably already exceeding the
kind of precision that can be claimed for them. In difficult situations
we might limit our team to a report of 0, 50, 100, where 50 is only
reported when they genuinely think that they are more than half
way. Only when they are finished may they claim 100%. This method
has the merit of being conservative.
Let us assume then that we have a relatively objective measure
of output.
Comparing
with Time
Clearly our measure cannot mean very much in the absence of something
of input against which to compare the percentage of output achieved.
The obvious comparative measure might be time elapsed. Therefore,
were we to find that we are 50% complete with 70% of the time allotted
for the task elapsed, this begins to tell us something and it is
probably (though not definitely) not good news.
In order to determine the reason behind such figures, we need to
ask more questions. And these questions are guided by the SEAM method
we saw in the previous article - i.e. the four types of reason why
tasks fall or appear to fall behind.
Type
1. Asking About the Possibility of Start Delay
One of the reasons might just be that we started late on this task
(relative to the baseline). Clearly then, we simply need to address
to the team the question:
"When did you actually start?"
The answer might indicate the following situation:

In this situation it is clear that the lower-than-expected progress
report is due to the later-than-expected start date.
We should also ask about 'Actual Finish' in cases where the task
has finished and 'Forecast Finish' in cases where it has not.
To summarise, the questions we have collected so far are:
· Progress (a percentage)
· Actual Start Date
· Actual or Forecast Finish date
If the actual start did not lag behind the planned (baseline) start,
then there are three other reasons to explain it. The situation
then looks like this:

We need to determine the reason for the gap between expected and
reported progress.
Type2. Asking about Absence
The reason for the low progress figure could be related to the unexpected
absence of some resources from the job - i.e. not getting the input
hours promised by the team. The question to ask here is simply,
"How many Actual Hours were expended so far?"
Type
3. Asking about Efficiency
The most common reason behind slow progress is related to a low
'production' rate, whose cause we must identify. Here we mean that
there are factors retarding the rate of production, at least as
compared to our baseline figure.
Candidates could include work resistance, lower than expected skills,
poor morale or attitude, adverse conditions - all of which reduce
to a poor estimate of the work. The questions to ask here are:
"What problems have been encountered?"
"What is the current forecast date of completion for this task?"
"What is the current forecast for effort (hours to be worked)
on this task?"
Some analysis will be required on the part of the project manager
to determine the average number of hours expected to be worked per
day and the nature of the calendar over the time this task will
occur. This must agree with the expected remaining duration of the
task.
We might also wish to ask about expenditures relating to purchases,
rentals, contracts and other non-labour costs.
The list of questions is now complete. These are:
· Progress (a percentage)
· Actual Start Date
· Forecast Finish Date
· Actual or Forecast Finish date
· Actual Hours
· Forecast Hours
· Problems
Type
4. Asking about Measure
It is possible that there is no problem at all, even thought the
reported percentage trails the expected one. This could be due to
the way in which we are measuring progress which might not be linear
or proportional to the amount of time passed. For example, marking
a up ditch before digging is vital but contributes nothing to the
measure of meters dug. Similarly, placing protective gear before
starting to paint itself provides no value to the 'score' of square
meters painted. Non-linear relationships can also occur through
the mechanism of a later speed-up due to the gaining of experience,
the amalgamation of multiple sub-tasks within a single one, or through
the poor selection of the progress metric.
Here we should check on the nature of what was actually done. The
forecast finish date asked of the team will help us to assess whether
or not there is a structural problem with the work or whether the
problem is simply one of the inadequacy of how we are measuring
progress.
Multiple
Causes
Of course it is possible for a combination of causes to fully explain
any problems we are seeing. We then require a means of analysing
this and breaking out the causes into the identifiable components
as we did above. This requires some analysis. There are two main
methods of attach here. One is the 'Earned Value' analysis and the
other, which is equivalent, is the 'Critical Ratio' method. These
will be subjects of our attention in future articles.
|