Earned Value Analysis and Pivot Tables
Manage Yourself – not Time!
Project Management for Innovation and High Risk
Writing Project Objectives
Writing Project Options
Writing Project Deliverables
Writing a Project Scope
Writing Project Constraints
Assessing Project Risk


Validating Data in Excel
The Purpose of Project Control
Diagnosing Project Problems
Asking the right questions of the team
Taking Corrective Action (Part 1)
Taking Corrective Action (Part 2)


Printing to Impress
Using a Deadline Symbol in Microsoft Project

Using Pivot Tables in Excel
The Power of a Project Management Database
Automatic Colour Changes on the Gantt Chart
Preparing and Entering Data
The Horizontal Screen Split
Scaling for Screen and Print
Improving Gantt Chart Appearance
Durations, Work and Resource Units
Assigning Part-Time Resources
Examining Costs
Costing Material-Type Resources
Tracking a Project - No.1
Tracking a Project - No.2
Grouping Tasks and Resources
Displaying Information in MS Project Tables
Reporting Cash flows
Using Outline Code Fields
Creating Filters
Creating Your Own Tables

Flexible Resource Costing
Project Server 2003


Tactical vs. Value Decision Making
Will Decision-makers learn from Project Managers?
How to Make Decisions
Formulating the Decision
Building a Decision Context
Elements of a Good Decision Process
Decision Options and Criteria
White Paper: Fending off the Lawyers
Overview of Decision-making tools & techniques

 

 

 

 

 

 

 

 

 

Examining Costs

Summary
Once resources (with defined standard rates or Cost per Use rates) have been assigned to tasks, costs are automatically calculated. Next we would want to inquire after the costs of the project. To see a total cost of the project, simply choose: Project - Project Information and click the 'Statistics' button.

Costs By Resources
Switch to a Resource oriented view such as 'Resource Sheet'.

  • Choose: View - Resource Sheet
  • Choose: View - Table - Cost

Modifying the Time scale
To modify the time scale:

  • Click the Zoom In or Zoom Out button on the toolbar .

You can use this to examine costs by the day month, quarter, half-year and longer

Costs By Task
To see a breakdown of the costs by task (and higher level WBS elements if you have them) switch to an appropriate table. First, however, make sure that you are on a task-oriented view such as Gantt chart.

  • Choose: View - Gantt Chart
  • Choose the 'cost' table
  • Click View - Table - Cost

The 'Total Cost' column contains the current cost forecasts of the project.

Costs By Time
Switch to the Task Usage view:

  • Choose: View - Task Usage
  • Right-click and choose Costs on the yellow time-based part of the screen

If you do not have a summary at the project level, choose: Tools - Options - (View Tab) and check the 'Project Summary' box. This will show you the cost of the project by period rolled up to the project level.

 

 

 