|
The Purpose of Project Control
The purpose of the project control or implementation phase is four-fold:
- To observe the work in progress.
- To ensure that it follows the plan sufficiently closely.
- To understand the underlying problems when it does not.
- To take appropriate action when necessary.
The medical analogy
The whole process is not very different from the case of a medical
doctor presented with a patient with symptoms. The doctor examines,
compares results with expectations (as provided by medical science),
diagnoses illnesses and prescribes treatment.
Project managers play the doctor role, examining the project (patient),
looking for symptoms (poor progress, excess expenditure, time delays),
seeking reasons (inefficient or absent resources,) and administering
anti-dotes (extending durations, providing additional resources).
In the project management context, the four steps mentioned above
are:
1. Monitoring
2. Tracking
3. Interpretation
4. Taking corrective action
The following schema describes the process and
flow of information:

Monitoring requires continual observation
and measurement of the 'actuals', that is actual starts and finishes,
actual effort, actual progress and efficiencies. It requires a systematic
reporting system involving the participation of team members who
provide feedback on a periodic basis.
Tracking involves the ongoing recording
and comparison of these 'actuals' with the plan, searching for significant
departures as an early warning of problems. Only by maintaining
an ongoing record of results can trends and patterns be detected.
The table below shows a typical representation of data collected
for a given progress measure for a particular task.
| Week |
Baseline |
Actual |
Forecast |
| 0 |
0 |
0 |
0 |
| 1 |
5 |
3 |
3 |
| 2 |
10 |
7 |
7 |
| 3 |
15 |
10 |
10 |
| 4 |
20 |
13 |
13 |
| 5 |
25 |
|
17 |
| 6 |
30 |
|
21 |
| 7 |
35 |
|
25 |
| 8 |
40 |
|
29 |
| 9 |
45 |
|
33 |
| 10 |
50 |
|
37 |
| 11 |
|
|
41 |
| 12 |
|
|
45 |
| 13 |
|
|
50 |
| 14 |
|
|
54 |
Interpretation is the attempt to
understand why deviations from the plan are occurring. This can
be assisted by certain reporting parameters which are designed to
indicate possible reasons for emerging problems. These include Earned
Value analysis and critical ratio analysis, topics to be covered
in future articles. In this case the actual values recorded are
trailing the baseline (originally predicted) values somewhat consistently,
indicating an ongoing problem regarding the rate of work.
This could be due to lack of skill, greater resistance encountered
on the job, or a mis-estimate of the work originally. The forecast
column indicates that at roughly current rates, the task will run
late. The last row also indicates that additional work will be required
for the task. The information can be shown graphically as follows:

Taking action means moving in a manner
to modify the current forecasts Possible actions could include adding
resources, extending durations or deadlines, overlapping tasks formerly
arranged in sequence or even modifying the nature of the task.
|