Earned Value Analysis and Pivot Tables
Manage Yourself – not Time!
Project Management for Innovation and High Risk
Writing Project Objectives
Writing Project Options
Writing Project Deliverables
Writing a Project Scope
Writing Project Constraints
Assessing Project Risk


Validating Data in Excel
The Purpose of Project Control
Diagnosing Project Problems
Asking the right questions of the team
Taking Corrective Action (Part 1)
Taking Corrective Action (Part 2)


Printing to Impress
Using a Deadline Symbol in Microsoft Project

Using Pivot Tables in Excel
The Power of a Project Management Database
Automatic Colour Changes on the Gantt Chart
Preparing and Entering Data
The Horizontal Screen Split
Scaling for Screen and Print
Improving Gantt Chart Appearance
Durations, Work and Resource Units
Assigning Part-Time Resources
Examining Costs
Costing Material-Type Resources
Tracking a Project - No.1
Tracking a Project - No.2
Grouping Tasks and Resources
Displaying Information in MS Project Tables
Reporting Cash flows
Using Outline Code Fields
Creating Filters
Creating Your Own Tables

Flexible Resource Costing
Project Server 2003


Tactical vs. Value Decision Making
Will Decision-makers learn from Project Managers?
How to Make Decisions
Formulating the Decision
Building a Decision Context
Elements of a Good Decision Process
Decision Options and Criteria
White Paper: Fending off the Lawyers
Overview of Decision-making tools & techniques

 

The Purpose of Project Control

The purpose of the project control or implementation phase is four-fold:

  • To observe the work in progress.
  • To ensure that it follows the plan sufficiently closely.
  • To understand the underlying problems when it does not.
  • To take appropriate action when necessary.

The medical analogy
The whole process is not very different from the case of a medical doctor presented with a patient with symptoms. The doctor examines, compares results with expectations (as provided by medical science), diagnoses illnesses and prescribes treatment.

Project managers play the doctor role, examining the project (patient), looking for symptoms (poor progress, excess expenditure, time delays), seeking reasons (inefficient or absent resources,) and administering anti-dotes (extending durations, providing additional resources).

In the project management context, the four steps mentioned above are:

1. Monitoring
2. Tracking
3. Interpretation
4. Taking corrective action

The following schema describes the process and flow of information:

Monitoring requires continual observation and measurement of the 'actuals', that is actual starts and finishes, actual effort, actual progress and efficiencies. It requires a systematic reporting system involving the participation of team members who provide feedback on a periodic basis.

Tracking involves the ongoing recording and comparison of these 'actuals' with the plan, searching for significant departures as an early warning of problems. Only by maintaining an ongoing record of results can trends and patterns be detected. The table below shows a typical representation of data collected for a given progress measure for a particular task.

Week Baseline Actual Forecast
0 0 0 0
1 5 3 3
2 10 7 7
3 15 10 10
4 20 13 13
5 25   17
6 30   21
7 35   25
8 40   29
9 45   33
10 50   37
11     41
12     45
13     50
14     54

Interpretation is the attempt to understand why deviations from the plan are occurring. This can be assisted by certain reporting parameters which are designed to indicate possible reasons for emerging problems. These include Earned Value analysis and critical ratio analysis, topics to be covered in future articles. In this case the actual values recorded are trailing the baseline (originally predicted) values somewhat consistently, indicating an ongoing problem regarding the rate of work.

This could be due to lack of skill, greater resistance encountered on the job, or a mis-estimate of the work originally. The forecast column indicates that at roughly current rates, the task will run late. The last row also indicates that additional work will be required for the task. The information can be shown graphically as follows:

Taking action means moving in a manner to modify the current forecasts Possible actions could include adding resources, extending durations or deadlines, overlapping tasks formerly arranged in sequence or even modifying the nature of the task.

 

 

 

Numerix Pty. Ltd. ABN 83 003 504 970 Telephone: 61 2 - 9279 0900 Fax: 61 2 - 9279 4141 email info@numerix.com.au