|
Taking Corrective Action (Part 2)
We continue with our examination of the corrective action alternatives
that are available to a project manager when progress begins to
lag behind expectations as shown in the diagram below. In the previous
article we looked at the implications of extending the duration
on the first task, leading either to a delay in the project finish
or at least a reduction in the amount of contingency available.
Option C: Overlap some tasks.
This is a popular method since it saves time but may not add to
the cost. However, we might ask after the reason for the presence
of the planned predecessor for task 2 in the first place - given
that we now seem willing to dispense with it. What was its importance
and what is implied by its omission? These questions need to be
considered before we simply overlap tasks. The other disadvantage
is that if the same resources are required on the now overlapping
tasks, a conflict is caused and this would have to be resolved.
Option D: Modify the method
This simply suggests that we tackle the task differently, even though
it has already started. This might involve the use of better processes,
more appropriate technology, higher skilled people or a total re-think
of the overall approach. Of course it would have been better to
identify these improvements earlier but we will exploit good ideas
whenever they strike us. The method is too general to lay out specific
consequences but they could include delays while we procure equipment
or train staff, cost-overruns incurred in that procurement or training,
the need to gain approvals for the new approach - among many other
possibilities.
Option E: Add Resources (Crashing)
To crash a project means to add resources to one or more critical
tasks in an effort to shorten their durations leading to a contraction
of the entire project. The primary consequence here is of course
a cost increase. This is due to a variety of factors. The time reduction
is rarely inversely proportional to the resource increase (the law
of diminishing returns) leading to inefficiencies and hence cost
increases. Also, as teams grow there need to be additional supervision,
catering, transport and other services that incur new costs. The
source of these additional resources may also become an issue. Are
they available? Do we draw them off other projects that will then
suffer from their absence? On the other hand, if we plan to make
use of the same people in the form of overtime, do we risk their
fatigue leading to potential safety or quality problems?
The question may then arise as to which task to crash. Planning
to wait until the last task might be risky, while crashing the first
one might not achieve acceptable results as it is already partially
complete. We might rather select task 2 and use the interval before
it starts to identify and prepare the additional team members so
that they will be performing to maximum productivity on that task.
This case is shown in the diagram below. We therefore plan to allow
it to start late but finish on time, thereby preserving the original
project end date.

F: De-Scoping
This usually means doing less, delivering a smaller slice of the
deliverable (and consequently associated project benefits) than
originally promised. This of course should not be done without negotiation
which again has consequences in terms of quality, client expectations,
credibility and professional reputation.
G: Motivate the Team
If we look after our team members in the good times they might just
look after us in the bad ones! Appealing to their sense of loyalty
and commitment to the project and the organisation might yield additional
effort in well-led teams. Of course there is a penalty. We are consuming
goodwill which will need to be replenished by acknowledgement, reward,
time-off or other means.

|